AACE 29R-03 Delay Attribution: A Practical Guide
AACE 29R-03 Delay Attribution: A Practical Guide
When a project slips, stakeholders do not only ask how late—they ask who owns the days. AACE International’s Recommended Practice 29R-03 (Forensic Schedule Analysis) is the industry’s common language for answering that question with a named method, not a spreadsheet anecdote.
This guide is a practitioner briefing: which method to pick, what data you need, and how to keep outputs defensible in reviews and disputes.
What RP 29R-03 is trying to solve
Forensic schedule analysis sits between:
- Planning quality (DCMA/GAO-style model integrity), and
- Prospective risk (Monte Carlo, weather models, SRI)
Delay attribution is retrospective (or near-real-time contemporaneous): given as-planned and as-built evidence, allocate variance among parties and causes.
If your network fails basic logic tests, forensic math becomes theater. Fix DCMA-class structural issues before arguing concurrency.
Three methods you will actually use
Bellator’s POST /api/v1/forensics/delay-analysis is built so results can cite the methodology name. That citation is not cosmetic—claims packages and expert reports expect it.
1. Windows analysis
Idea: Divide the project into time windows. Update the schedule at each window boundary and measure critical path impact inside the window.
Best when:
- You have periodic updates (monthly/biweekly status cycles)
- You need a narrative that tracks the evolving critical path
- Stakeholders already manage by reporting periods
Watch-outs: Window boundaries can be gamed; document why windows were chosen.
2. Contemporaneous period analysis
Idea: Rely on the schedules as they existed at the time, not a reconstructed perfect model. Emphasizes what managers knew when decisions were made.
Best when:
- Dispute focuses on decision timing and notice
- You have a clean archive of periodic schedule submissions
Watch-outs: Garbage-in from poor contemporaneous schedules stays garbage-out—disclose data quality.
3. Collapsed as-built (but-for)
Idea: Start from the as-built network and remove delay events (or party-caused activities) to estimate a but-for completion.
Best when:
- As-built logic is trustworthy
- You need a but-for completion story for a specific set of events
Watch-outs: Highly sensitive to which activities you collapse and how concurrent delays are treated.
Concurrent delay in plain language
Concurrent delay means owner- and contractor-caused delays overlap such that neither party can claim the full period as exclusively theirs under the contract’s rules.
Good analysis:
- Identifies overlapping windows on the critical path (not every noisy activity)
- Separates excusable / compensable / non-excusable categories per contract
- States assumptions when the network cannot support a unique split
Never hide concurrency inside a single “weather” bucket without dates and path proof.
Worked scenario (illustrative)
Suppose a data-center build with status updates at month ends:
| Window | Critical path theme | Observed slip (days) | Preliminary attribution |
|---|---|---|---|
| Jan | Foundation rebar | 5 | Contractor productivity |
| Feb | Long-lead switchgear | 12 | Owner late free-issue |
| Mar | Both path & switchgear | 8 | Concurrent (split per contract) |
A Windows analysis would restate the critical path each month and sum party impacts with concurrency rules applied in March. A collapsed as-built might instead remove owner free-issue delay activities from the as-built model and recompute finish.
The numbers will differ; the report must say which method produced them.
Data you need before calling an API
| Data | Why |
|---|---|
| Current / update schedules | Progressed network |
| Baseline or as-planned | Reference for variance |
| Status dates / window bounds | Periodization |
| Delay event register (optional but powerful) | Cause coding (owner/contractor/force majeure) |
| Calendars & constraints | True critical path |
Import P6/XER or MSP XML first if needed (import guide), then pass normalized tasks to forensics endpoints. Comparison endpoints remain stateless—send all schedules inline.
Example request shape
curl -X POST "https://api.bellatorsi.com/api/v1/forensics/delay-analysis" \
-H "Content-Type: application/json" \
-H "x-api-key: YOUR_API_KEY" \
-d '{
"methodology": "windows",
"status_date": "2026-03-31",
"baseline_schedule": { "tasks": [/* as-planned */] },
"current_schedule": { "tasks": [/* updated */] },
"windows": [
{ "name": "2026-01", "start": "2026-01-01", "end": "2026-01-31" },
{ "name": "2026-02", "start": "2026-02-01", "end": "2026-02-28" }
]
}'
Field names may vary by API version—confirm against the API reference and playground schema for forensics-delay-analysis. Always retain the methodology field in stored reports.
How this differs from Schedule Risk Index
| Delay analysis (29R-03) | Schedule Risk Index | |
|---|---|---|
| Time posture | Mostly retrospective / contemporaneous | Forward-looking structural risk |
| Output | Attribution of slip | 0–100 risk posture pre-simulation |
| Typical user | Claims, PMO forensics | Portfolio risk, go/no-go reviews |
Read: Schedule Risk Index: what the numbers mean.
Reporting checklist (citable package)
- Methodology named (Windows / Contemporaneous / Collapsed As-Built)
- Source schedules identified (baseline, updates, as-built)
- Calendars and data-date disclosed
- Critical path exhibits per period
- Concurrency treatment stated
- Contract clauses referenced for compensability (legal, not API)
- Re-run hash or input snapshot retained for audit
Next steps
- Validate model integrity first with DCMA 14-Point
- Exercise the endpoint in the Playground
- Review standards mapping for AACE coverage by tier
Sources
- AACE International — Recommended Practice 29R-03, Forensic Schedule Analysis
- GAO Schedule Assessment Guide (credible schedules as a prerequisite to forensics)
- Bellator forensics — delay analysis (Tier 2)
Share
Related posts
Part 1 · DCMA Deep Dive
What is DCMA 14-Point Schedule Analysis?
DCMA 14-Point is the Defense Contract Management Agency’s PAM 200.1 checklist for schedule integrity. Learn what the checks cover and how to automate them with Bellator.
5 min readSchedule Risk Index: What the Numbers Mean
The Schedule Risk Index (SRI) is a deterministic 0–100 pre-simulation risk signal built from network structure and CPM diagnostics—not a probabilistic finish date.
3 min readPart 2 · DCMA Deep Dive
Common DCMA Findings and How to Fix Them
A field guide to frequent DCMA PAM 200.1 failures: what the finding means, how to confirm it, and the fastest credible fix in P6 or MS Project.
4 min read